Current status – August 27

Elevator #4 located within north-west corner of Building 6 was closed on August 15 and will reopen on September 18. This is the final elevator to be modernized out of a total of 10 elevators within this modernization work.

See the floor plan with locations of all 10 elevators and the status of modernization work.

We regret the inconvenience caused. Questions: facilities@macewan.ca.

Background: Elevator closure in Buildings 5, 6, 7 and 8

The 10 elevators in Buildings 5, 6, 7 and 8 are original to the buildings and built in 1993. Their control system are obsolete and parts are no longer available. This project will replace the control system while simultaneously upgrading the elevators to meet the City of Edmonton’s current code.


From Facilities